Employer |
Central Anatolia Development Agency |
Dates |
25/11/2014 - 12/11/2015 |
Designer |
Çevre Yapı Proje Yönetim Ltd. Şti. Gökhan Berk |
Services Provided |
Preparation of architectural, civil engineering, mechanical, electrical, landscape architecture and infrastructure engineering design and drawings. Preparation of the cost estimate and works contract tender documents. |
Project Information |
The project is located in the Sivas Organized Industrial Zone and sits on a parcel of around 20.000 m2. It consists of one administrative building with a total construction area of around 2.000 m2 and of workshop units with varying sizes with a total closed area of around 8.000 m2. The project is funded by EU and the Republic of Turkey under IPA programme. |
Sahrayıcedit Mahallesi İnönü Caddesi No:47/I 34734 Kadıköy İstanbul Turkey